Assessment of EoI:239



EoI Metadata

Performance of EoI 239 in East Africa Drylands - Percentile by Average Score


Section 1 - Experience & strengths relevant to the proposed Indigenous territory, landscape/seascape (Total Points: 30)

A) Importance of the landscape/seascape/indigenous territory for biodiversity, with additional consideration to climate benefits.
1. Is the proposed territory/landscape/seascape a globally important area for biodiversity?

Scoring:

  • Not significant;

  • Low Significance;

  • Moderate Significance;

  • Medium-high Significance;

  • High Significance;

  • Exceptional Significance

Reviewer A: 2/5 Reviewer B: 4/5

Average: 3/5

Evidence A: It is part of the savanna grass land, covering two counties

Evidence B:The project focuses on a large ecosystem which includes protected wildlife areas as well as private ranches and community lands occupied by pastoralists. It is an ecosystem where all users are inter-dependent.


2. Is the area important for climate mitigation?

Scoring:

  • >50 t/ha - Low;

  • 50 - 100 t/ha - Moderate;

  • >100 t/ha - High

Reviewer A: NA/2 Reviewer B: 1/2

Average: 1/2

Evidence A: there is n mention of this

Evidence B:It is important because it over-exploitation of one area affects the sustainability of the whole. The conservancy also deals in carbon sequestration.


B) Geographical focus in an area under IPLC governance.
3. Is the area held and managed by IPLC under community-based governance systems?

Scoring:

  • IPLC governance (rights and institutions) not evident;

  • Project areas are marginally under IPLC governance (spatially or politically);

  • Project areas are partially under IPLC systems of governance (spatially or politically);

  • Project areas are largely under IPLC governance, but IPLC rights and/or institutions face significant constraints;

  • Project areas are held and managed under IPLC governance systems, with some limitations;

  • Project areas are held and managed under strong and active IPLC governance systems

Reviewer A: 2/5 Reviewer B: 5/5

Average: 3.5/5

Evidence A: Heavy partnership and governance with NRT and National governement

Evidence B:The project brings together four different pastoralist communities= the Samburu, Turkana, Borana and Somali. They contribute significantly to the sustainability of the ecosystem.


4. Does the proposal explain the unique cultural significance of the area to IPLCs?

Scoring:

  • No explanation given of unique significance to IPLCs;

  • Significance of site(s) vaguely described;

  • Unique significance of project site(s) clearly explained

Reviewer A: NA/2 Reviewer B: 1/2

Average: 1/2

Evidence A: The explanation given was more for the leadership and management of the conservancy but no explanation is given for unique cultural significance of all the four communities represented

Evidence B:Each of the 4 communities have rich unique systems that would be interesting to include.


C) Vulnerability of the proposed IPLCs as well as their lands/waters/natural resources to threats.
5. Is the area vulnerable to threats/current risk of negative impacts to IPLC and biodiversity without action?

Scoring:

  • No evident threats;

  • Low threats;

  • Moderate threats;

  • Medium-high threats;

  • High threats;

  • Requires urgent action

Reviewer A: 4/5 Reviewer B: 4/5

Average: 4/5

Evidence A: 80% of land being covered by an invasive plant that prevents the growth of grass is quite high considering that grass is needed for supporting pastoralists livelihoods

Evidence B:All parts are important for the success of the whole.


D) Opportunities for ICI results - including enabling policy conditions, positive government support and presence of successful IPLC-led conservation initiatives that could be scaled up.
6. Are enabling policy conditions in place for IPLC-led conservation in the proposed area?

Scoring:

  • Legal and policy frameworks in project areas undermine IPLC governance (either actively or through absence);

  • Legal and policy frameworks recognize limited rights for IPLCs over their lands and/or resources;

  • Legal and policy frameworks recognize rights over lands and resources but with constraints (e.g., lack implementing regulations);

  • Legal and policy frameworks actively promote the recognition of IPLC governance

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: Very good regulations without implementation plans

Evidence B:National and county governments provide along with legal and policy frameworks.


7. Is there active government support for IPLC-led conservation in the proposed country/area?

Scoring:

  • National or sub-national governments are actively opposed to IPLC-led conservation;

  • National or sub-national governments have recognized the importance of IPLC-led conservation;

  • National or sub-national governments have implemented some support for IPLC-led conservation;

  • National or sub-national governments are actively engaged in the promotion of IPLC rights and IPLC-led conservation

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: IPLCs in Isiolo are well supported by the National and County Governemnt

Evidence B:See above.


8. Are there successful IPLC-led conservation initiatives in the proposed area that provide a foundation for scaling up?

Scoring:

  • No IPLC-led conservation initiatives have been implemented;

  • Few IPLC-led conservation projects have been implemented in pilot stages only;

  • Some IPLC-led conservation projects have been implemented beyond pilot stages;

  • Relevant IPLC-led conservation projects have been well established for many years

Reviewer A: 3/3 Reviewer B: 3/3

Average: 3/3

Evidence A: They have been awarded and recognised twice as the best community and indigenous led conservation by NRT

Evidence B:All conservancies are in close collaboration.


E) Synergies with existing investments.
9. Are there other initiatives (relevant projects) that provide complementary support for IPLC-led conservation in the geography?

Scoring:

  • Few to no complementary projects/investment;

  • Complementary projects/investments are small, or are tangentially related to project goals;

  • Complementary Projects/investments align strongly with project goals and investments are substantial

Reviewer A: 1/2 Reviewer B: 2/3

Average: 1.5/2

Evidence A: there are few projects funded by USAID through NRT, like the beading project, carbon credit and livestock trading

Evidence B:Many of them exist in the in the region.



Section 1:

Reviewer A Total Score: 16/30
Reviewer B Total Score: 26/30

Average Total Score: 21/30



Performance of EoI 239 in East Africa Drylands - Percentile by Average Score (Section 1)


Section 2 - Quality and ability of the proposed approach and interventions to achieve transformational impact that generate the global environmental benefits (Total Points: 40)

A) Quality of proposed approach and ability to support traditional structures, knowledge and community practices in the delivery of global environmental benefits.
1. Is the proposed approach well aligned with the overall objective of the ICI to: Enhance Indigenous Peoples' and Local Communities' (IPLCs) efforts to steward land, waters and natural resources to deliver global environmental benefits?

Scoring:

  • Weakly aligned;

  • Partially aligned;

  • Well aligned;

  • Exceptionally well aligned

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: The IPLCs are well placed in the management plan and are beneficiaries in the whole conservation plan

Evidence B:Pastoralism and wildlife conservation are complementary.


2. Does the EoI present a clear and convincing set of activities and results?

Scoring:

  • The objectives and approach for this project lack clarity and cohesion, and/or do not appear to be realistic for the context;

  • Activities & results defined but logic (Theory of Change) is incomplete;

  • Activities and results are well-defined and cohesive but some aspects require clarification;

  • The project has clear objectives and a cohesive approach with relevant activities for the context and timeline

Reviewer A: 6/6 Reviewer B: 6/6

Average: 6/6

Evidence A: So many activities but relevant to the conservancy

Evidence B:They are but need actual timing.


3. Will the project (objectives and activities) contribute to overcoming identified threats and putting in place necessary enabling opportunities for IPLC-led conservation?

Scoring:

  • Objectives and activities do not clearly address identified threats and opportunities;

  • Contributions to addressing the threats and opportunities are low;

  • Contributions to addressing threats and enabling conditions are slightly over-ambitious;

  • The impact on threats and enabling conditions can be realistically accomplished and are sufficiently ambitious for the projects' context

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: Getting rid of the invasive species and the expansive area it covers is abit over ambitious

Evidence B:They can be achieved.


4. Are the activities achievable within a $500,000 to $2,000,000 USD budget range in a period of 5 years of project execution?

Scoring:

  • Activities/results not aligned with EoI range of investment;

  • Activities/results Partially aligned with EoI range of investment ;

  • Activities/results Well aligned with EoI range of investment ;

  • Activities/results Exceptionally well aligned with EoI range of investment

Reviewer A: 2/3 Reviewer B: 2/3

Average: 2/3

Evidence A: yes very well achievable

Evidence B:The project has previously handled less amounts of financial support,


5. Does the EoI include significant and concrete sources of co-financing?

Scoring:

  • None;

  • Small;

  • Moderate;

  • Significant

Reviewer A: 2/3 Reviewer B: 2/3

Average: 2/3

Evidence A: the sale of beads and livestock are very low investments, but with NRT and USAID , there is moderate co financing

Evidence B:Moderate but some is long term.


B) Potential of the proposed activities to achieve IPLC-led transformational impact that generate global environmental benefits.
6. Are the estimated Global Environmental Benefits (GEF core indicators) substantial and realistic?

Scoring:

  • Not provided;

  • Very Low (below 10,000 Ha);

  • Moderate (between 100,000 - 500,000 Ha);

  • High (between 500,000 - 1,000,000 Ha);

  • Very high above 1,000,000 Ha

Reviewer A: 2/5 Reviewer B: 3/5

Average: 2.5/5

Evidence A: The proposal indicates 34,000Ha

Evidence B:The amounts the project has been handling are moderate.


7. Are the additional cultural and livelihoods results contributing to project objectives?

Scoring:

  • No provided cultural or livelihood indicators for the project;

  • Indicators proposed but are not clearly aligned with project goals;

  • Indicators proposed and are moderately aligned with project goals;

  • Additional cultural and/or livelihood indicators clearly derive from project goals

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: There is mention of beads and livestock sale

Evidence B:Not all of them are detailed but yes they are at the core of the project.


8. Does the EoI provide a clear and robust vision for long-term sustainability?

Scoring:

  • Vision for long-term sustainability not provided;

  • This project does not seem to have a clear long-term impact;

  • This project will create medium-term benefits for biodiversity and IPLC governance, which future funding will hopefully build upon;

  • This project will ensure long-term benefits to biodiversity and IPLC systems of governance

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: This is clear throughout the proposal

Evidence B:There are clearly provided and there are long term commitments. Better grazing means better and healthier herds, hence better livelihoods,


C) IPLC-led conservation that advances national and global environmental priorities.
9. Does the EoI build on and contribute to national priorities as defined in NBSAPs and/or NDCs?

Scoring:

  • Contributions not provided;

  • The project is weakly related to either national priorities;

  • The project appears to be tangentially related to national priorities;

  • The proposal reflects an understanding of the national policy priorities and clearly positions the project in relation to those priorities

Reviewer A: 3/3 Reviewer B: 3/3

Average: 3/3

Evidence A: Well illustrated contributions to NCCAP 2013, 2017

Evidence B:Through partnership with county and national governments there have been contribution/


D) Demonstrated gender mainstreaming in all activities.
10. Does the EoI provide a clear and robust approach to gender mainstreaming?

Scoring:

  • Gender mainstreaming approach is absent;

  • Gender mainstreaming approach is weak;

  • Gender mainstreaming approach is moderately thought through (if there are a few activities as 'add ons');

  • Significant and well-thought through approach to gender mainstreaming

Reviewer A: 2/3 Reviewer B: 3/3

Average: 2.5/3

Evidence A: There is mention of women and youth activities, and the bead work is primarily done by women and this is their contribution in a big way

Evidence B:The iproject is clearly aware of the constitutional gender requirements.


E) Innovation and potential to scale up.
11. Do the proposed activities and results demonstrate innovation and potential for transformative results at scale?

Scoring:

  • None demonstrated;

  • Low demonstrated potential;

  • Moderate demonstrated potential;

  • Medium-high demonstrated potential;

  • High demonstrated potential;

  • Exceptional demonstrated potential

Reviewer A: 3/5 Reviewer B: 4/5

Average: 3.5/5

Evidence A: 34,000 Ha is not small and knowing that it will reach 4 indigenous communities

Evidence B:To the extent in which they are detailed.



Section 2:

Reviewer A Total Score: 28/40
Reviewer B Total Score: 35/40

Average Total Score: 31.5/40



Performance of EoI 239 in East Africa Drylands - Percentile by Average Score (Section 2)


Section 3 - Qualifications and experience of the Organization (Total Points: 30)

A) Indigenous Peoples or Local Community organization legally recognized under national laws.
1. Is the EoI led by an IPLC organization?

Scoring:

  • IPLC appear to be beneficiaries only;

  • Combination/partnership of IPLC organizations and NGOs, and plans to build IPLC capacity over the project term are clear;

  • IPLC-led approach, NGOs in more limited, defined roles (such as fiduciary);

  • Fully IPLC composed and led approach

Reviewer A: 4/6 Reviewer B: 6/6

Average: 5/6

Evidence A: The leadership and management of the conservancy is all IPLC, but there is also partnership with NRT in the management and other county and national parastatals

Evidence B:Yes. Other skills are accessed from outside.


2. Does the lead proponent demonstrate on-ground leadership relevant to the proposed work?

Scoring:

  • None demonstrated;

  • Limited demonstration of relevant on-ground leadership;

  • Demonstrated on-ground leadership relevant to the proposed work;

  • Exceptional and long-standing on-ground leadership relevant to the proposed work

Reviewer A: 4/6 Reviewer B: 6/6

Average: 5/6

Evidence A: The lead does demonstrate hands-on ground leadership absolutely

Evidence B:The project has been sensitive to ensure inclusion and balance of all the four pastoralist communities in the project area.


C) Proven relevant experience in working with IPLC networks, alliances and organizations/ strength of partnerships on the ground.
3. Does EoI demonstrate that the lead proponent has strong partnerships, particularly with other IPLC organizations, to carry out the work?

Scoring:

  • No partners defined;

  • No IPLC partners identified;

  • IPLC organizations are listed as implementing partners but without clear scope (roles in project design or governance);

  • IPLC organizations are listed as implementing partners with clear roles (in project design or governance);

  • Strong IPLC partnerships that play a central role in design, governance, and implementation of the project;

  • Strong IPLC partnerships have a central role in design, governance and implementation of the project and linkages with national or regional IPO networks

Reviewer A: 2/5 Reviewer B: 5/5

Average: 3.5/5

Evidence A: The partnerships mentioned by the applicant in Q21 are only NRT, ACTION AID and a research institute, no mention of any IPLC organizations

Evidence B:Partnership is well articulated.


D) Technical expertise and capacity to address environmental problems, root causes and barriers.
4. Does EoI demonstrate technical capacity of lead proponent and partners to deliver the proposed results?

Scoring:

  • No skills demonstrated;

  • The skills and experiences outlined have little or no relation to the project activities;

  • There is some lack of clarity or some gaps in the capacities necessary to implement the project;

  • The activities clearly show how they plan to fill capacity gaps over the course of the project;

  • They seem to have adequate skills and capacity for the project but do not have experience with GEF projects;

  • The lead organization and project partners clearly communicate that they have all the skills and experience necessary to implement the project activities. Also, have past experience with GEF funded projects.

Reviewer A: 1/5 Reviewer B: 5/5

Average: 3/5

Evidence A: the skills and experiences outlined have little or no relation to the project activities, may be this question was not understood by the applicant

Evidence B:They have the necessary skills and can access what they do not have.


E) Project Management capacity.
5. Does the EoI demonstrate project & financial management capacity needed for scale of proposed effort?

Scoring:

  • Very limited (no criteria met);

  • Some capacity but would require support (1/3 criteria);

  • Moderate capacity (2/3 criteria met);

  • Very strong (all criteria met) with demonstrated past performance

Reviewer A: 2/6 Reviewer B: 4/6

Average: 3/6

Evidence A: There is no evidence given of demonstrated financial competency

Evidence B:Most of the criteria are met on a moderate scale.


6. Does lead organization have experience with safeguards and other standards required by GEF?

Scoring:

  • Answered no;

  • Answered yes but with weak or lacking explanation to the extent;

  • Answered yes with clear explanation of the extent

Reviewer A: 1/2 Reviewer B: 2/2

Average: 1.5/2

Evidence A: yes but no explanation

Evidence B:There is awareness of safeguards.



Section 3:

Reviewer A Total Score: 14/30
Reviewer B Total Score: 28/30

Average Total Score: 21/30



Performance of EoI 239 in East Africa Drylands - Percentile by Average Score (Section 3)